Chapter -3
Installation of Hand Pump and Construction of Platform,
Drain and Sokage pit

S.No Description of Item Unit Rate in Rupees
1 Labour charges for installation of India Mark II Hand Pump with 30 meter long 32 mm dia. riser pipe assembly and all other accessories including transportation of Hand Pump from specified departmental stores to site. Each 214
2 Add to item No.1 above for fixing the extra length of riser pipe assembly beyond 30 meters Meter 6
3 Construction of 76 cm.x 76 cm x 40 cm. foundation block in 1:2:4 cement concrete for fixing the pedestal of Hand Pump including excavation, cost of material and labours etc. complete. Each 334
4 Construction of cement concrete platform as per design around the hand pump in 1:2:4 cement concrete including excavation, centering, shuttering, cost of all the materials and labour and curing etc complete. Each 1590
5 Construction of cement concrete drain as per UNICEF design in 1:2:4 cement concrete including excavation, centering, shuttering, cost of all the materials and labour and curing etc complete. Meter 148
6 Construction of 1.20 m x 1.20 m x 0.20 m cement concrete washing platform in cement concrete 1:2:4 including excavation, centering, shuttering, cost of all the materials and labour and curing etc. complete. Each 749
7 Construction of sokage pit of 70 cm dia. and 1.0 m deep including excavation, brick lining at top in 1:4 cement mortar, filling of boulder, broken bricks etc. and cost of all the materials and labour and curing etc complete. Each 203